Skip to main content
  • Accessibility And Screen Reader Options
  • English
  • मराठी
  • हिन्दी

A A A

Homepage Logo Mumbai Metro Rail Corporation Ltd. (JV of Govt. of India and Govt. of Maharashtra)

mmrc

Search form
Home MMRC
  • Home
  • About MMRC
    • Know Your Metro
    • Our Vision, Mission & Values
    • Board of Directors
    • Key Management Team
    • Our Organization
    • Managing Director
    • Reports & Documents
    • MOA & AOA
    • Annual Report
  • Project
    • Project Route
    • Project Timeline
    • Project Funding
    • Illustrative Designs
    • Technology
    • Typical Utility Shifting Plan
    • Project Consultants
    • Benefits of Metro Line 3
    • Environmental Benefits
    • Rehabilitation & Resettlement (R&R)
      • FLGRC/SLGRC
      • Public Consultation
      • Final BSES
      • Lottery Result
      • Policy / Project Documents
      • In - situ R&R Office Address
      • BSES Survey Maps
      • Building wise Allotment List
      • Rehabilitation Building Occupation Certificate
      • Public Notices
    • Projects Reports & Documents
    • NOC
    • Notice
    • Typical Traffic Diversion Plan
  • People Connect
    • FAQ
      • FAQ on Kalbadevi & Girgaon
      • FAQ on Aarey
    • Facts Of Aarey
      • Note On Aarey
      • MMRC Ad
    • Quick Facts
  • Tenders
    • Civil
    • System
      • Electrical
      • Signalling & Telecom
      • Rolling Stock
      • IT
      • Depot (M&P)
      • O & M
    • Planning
    • Miscellaneous
    • Awarded Contracts
    • MMRC Contractors
    • eTender
    • EOI-MoHUA
  • Media
    • Gallery
      • Photo Gallery
      • Video Gallery
    • News
    • Newsletters
    • MD Speaks
    • Press Releases
    • Social Media
      • Facebook
      • Instagram
      • Twitter
      • Youtube
  • Careers
    • Recruitment
    • Internship Policy
  • RTI
    • RTI (GOI)
    • RTI (GOM)
    • RTI ACT 2005
    • RTI/SANAD
    • PIO/APIO
  • Vigilance
    • Chief Vigilance Officer
    • Notice
    • Vigilance Awareness
  • Contact Us
    • How to reach us
    • Compliance Officer & Company Secretary
  • Policies
Flash News
MMRC

Flash News

एनसीपीएने नूतनीकरण केलेल्या दिलीप पिरामल आर्ट गॅलरीचे मेट्रो-३ वरील छायाचित्र प्रदर्शनासह शुभारंभ
NCPA inaugurates its Renovated Art Gallery with photo exhibition on Metro Line-3
Design, Manufacture, Supply, Installation, Testing & Commissioning of Lot I: Blow Down Plant along with Comprehensive Maintenance Service, and Lot II: Well Wagon, for Project “Mumbai Metro Line-3
Design, Manufacture, Supply, Installation, Testing & Commissioning of Lot I: Blow Down Plant along with Comprehensive Maintenance Service, and Lot II: Well Wagon, for Project “Mumbai Metro Line-3
“Design, Manufacture, Supply, Installation, Testing & Commissioning and Comprehensive Maintenance Service of Rail-cum-Road Diesel Shunter” for Project Mumbai Metro Line-3
मुं.मे.रे.कॉ. तर्फे "मराठी भाषा संवर्धन पंधरवडा" साजरा मराठी बोला, मराठीतच शिका, मराठी भाषा टिकवा - अभिनेते सुमित राघवन
Civil Maintenance Contract for R & R Sites, MMRCL Transit Office and Civil & Electrical Work at MMRCL Hallmark Business Plaza 2nd & 8th Floor Offices and other allied works under Mumbai Metro Line III of MMRCL.
मुं.मे.रे.कॉ.च्या वतीने ३००० झाडांचे मूळ जागी वृक्षारोपण मोहिमेला सुरूवात
MMRC begins In-situ plantation drive of 3,000 trees
Design, Manufacture, Supply, Installation, Testing & Commissioning and Comprehensive Maintenance Service of Rail-cum-Road Diesel Shunter” for Project Mumbai Metro Line-3
  1. Home
  2. Package - 2

Package - 2

MMRC
Submitted by admin on Tue, 11/22/2016 - 15:01
 Sr. No.Nature of WorkStatus
1Tunneling & Segment Production Progress

TBM - 1 Tunneling completed (TBM dismantalling in progress)

Temporary ring: Scope - 12 Completed

CST - SKD: Scope - 476 Completed

SKD - SGG: Scope - 499  Completed

SGG - SGR: Scope - 1,110 Completed

SGR - SMC: Scope - 635 Completed

TBM - 2

Temporary ring: Scope - 12 Completed

CST - SKD: Scope - 482 Completed

SKD - SGG: Scope - 488  Completed

SGG - SGR: Scope - 1,123 Completed

SGR - SMC: Total progress - 422, Scope - 639

Note:

TBM 2 stopped due to Parsi Fire Temple Issue on 20.07.2018 and resumed on 30.11.18

Second time stopped on 6.12.18 & resumed on 10.12.18

The productivity of TBM 2 is low due to unanticipated ground condition

Segment Production

Permanent Rings (including Upline & Downline)

SCS - SKD: Scope - 961 Completed

SKD - SGG: Scope - 713 Completed

SGG - SGR: Scope - 1,913 Completed

SGR - SMC: Scope - 991 Completed

Temporary Rings (including Upline & Downline)

SCS: Scope - 20 Completed

SKD: Scope - 277 Completed

SGG: Scope - 313 Completed

SGR: Scope - 287 Completed

2Excavation 

CST Station

Launching shaft: Scope - 25,859 Cum. Completed

Station Box (with extended concourse) - Scope - 1,26,691 Cum. Completed

Entry and Exit- Total Progress - 11,310 Cum. Scope - 29,956  Cum.

Grant Road

Station Box- Total Progress - 59,938 Cum. Scope - 1,03,536 Cum.

EE-1(Phase-02) - Total Progress - 8,829, Scope - 9,329

EE-2(Phase-05) - Total Progress - 2,364, Scope - 2,959

EE-3 (Phase-08) - Scope - 2,686

Girgaon

EE-2 (Swami Niwas) - Scope - 2,010

Station Box EE-3 (Extended conc.) -  Total Progress - 24,036, Scope - 1,39,980

Kalbadevi

Station Box- Total Progress

K-1 Box - Total Progress - 2,307, Scope - 26,621

K-2 Box -  Total Progress - 11,798, Scope - 52,000

3Base Slab Progress

CST

Station Box: Total Progress - 180, Scope - 250 

4Secant Piling Progress 

CST Station

Primary pile - Station Box: Scope - 359 Completed

Secondary pile Station Box: Scope - 352 Completed

Primary pile - Entry & Exit: Total progress - 620, Scope - 662

Secondary pile - Entry & Exit: Total progress - 628, Scope - 661

Grant Road Station

Primary pile: Total progress - 370, Scope - 371

Secondary pile: Scope - 373 Completed

Primary pile - Entry & Exit: Total progress - 53, Scope - 56

Secondary pile - Entry & Exit: Total progress - 48, Scope - 56

Girgaon Station

Primary pile Station Box: Scope - 353 Completed

Secondary pile Station Box: Total progress - 340, Scope - 345

Primary pile - Entry & Exit: Scope - 88 Completed

Secondary pile - Entry & Exit: Scope - 88 Completed

Kalbadevi Station K-2 Box

Primary Pile Station Box: Scope - 167 Completed

Secondary Pile Station Box: Scope - 167 Completed

Kalbadevi Station K-1 Box

Primary Pile Station Box: Scope - 96 Completed

Secondary Pile Station Box: Scope - 96 Completed

5Rehabilitation & Resettlement 

Rehabilitation & Resettlement is in progress.

Compensation meeting in progress with project affected residents in Kalbadevi and Girgaon.

6Building condition Survey

Pre - Condition Survey

Total Progress - 884

Scope - 1,004

Note: Additional 25M Topography survey on either of ZOI completed

7Tree Cutting/transplantation

CST - Total Progress - 47 , Scope - 91

CST - Transplantation - Total Progress - 62 , Scope - 97

Grant Road  - Total Progress - 28 , Scope - 28

Grant Road Transplantation - Total Progress - 21 , Scope - 21

Girgaon - Total Progress - 10 , Scope - 11

Girgaon Transplantation - Total Progress - 9 , Scope - 9

New Plantation at Aarey Colony  - Total Progress - 205 , Scope - 35

8 Traffic Diversion 

Permission for Traffic Diversion at Girgaon station received and  trial run road diversion started from 18th May 2017.

Trail run for traffic diversion at Grant road done on 20th July’2017 and road diversion started from 27th July’2017.

9Geo-technical investigation

Geo-technical investigation for Stations as well as Tunnel completed.

10Barricading

Barricading for CST Station Box, Wadala Casting Yard and WTC completed.

Barricading in Grant Road completed for Garden Side.

Structural Steel barricading for Median done at Grant Road.

Barricading in Girgaon completed for 619 RM out of 619 RM (Approx.)

Barricading in Kalbadevi station started as per land available on 29.09.18

Upload File: 
PDF icon project-status-2.pdf
Date: 
Sunday, February 9, 2020 - 15:00
Package Type: 
Package-2
Gallery: 
Package - 2 ( CST-Kalbadevi-Girgaon-Grant Road )
MMRC

Recent News

mmrc
नव्या वर्षात धावण्यासाठी भुयारी मेट्रोचे काम ऑन स्पीड
+29 Mar 2023
आरे कारशेड में उतरेगी मेट्रो-3 की नई रेक
+29 Mar 2023
CITY TO GET BACK SPACE TAKEN BY METRO 3 WORKS
+29 Mar 2023
MUMBAI STARTS RECLAIMING ROADS
+29 Mar 2023
MUMBAI STARTS RECLAIMING ROADS
+29 Mar 2023
मेट्रो ३ : रुळांचे ५८ टक्के काम पूर्ण
+27 Mar 2023
Previous Pause Next
MMRC

About MMRC

  • Tenders
  • Project
  • News
  • Contact Us
  • eTender
MMRC

Helpful Information

  • Project Route
MMRC

Policy

  • MMRC Green Policy
  • Disclaimer
  • Privacy Policy
MMRC

Other Govt Sites

  • Govt of India
  • MoHUA
  • Indian Railways
  • Govt of Maharashtra
  • MMRDA
  • Other Metros
MMRC
  • mmrc
  • mmrc
  • mmrc
MMRC

MMRC © 2019. All rights are reserved.

  • mmrc
  • mmrc
  • mmrc
Top