Skip to main content
  • Accessibility And Screen Reader Options
  • English
  • मराठी
  • हिन्दी

A A A

Homepage Logo Mumbai Metro Rail Corporation Ltd. (JV of Govt. of India and Govt. of Maharashtra)

mmrc

Search form
Home MMRC
  • Home
  • About MMRC
    • Know Your Metro
    • Our Vision, Mission & Values
    • Board of Directors
    • Key Management Team
    • Our Organization
    • Managing Director
    • Reports & Documents
    • MOA & AOA
    • Annual Report
  • Project
    • Project Route
    • Project Timeline
    • Project Funding
    • Illustrative Designs
    • Technology
    • Typical Utility Shifting Plan
    • Project Consultants
    • Benefits of Metro Line 3
    • Environmental Benefits
    • Rehabilitation & Resettlement (R&R)
      • FLGRC/SLGRC
      • Public Consultation
      • Final BSES
      • Lottery Result
      • Policy / Project Documents
      • In - situ R&R Office Address
      • BSES Survey Maps
      • Building wise Allotment List
      • Rehabilitation Building Occupation Certificate
      • Public Notices
    • Projects Reports & Documents
    • NOC
    • Notice
    • Typical Traffic Diversion Plan
  • People Connect
    • FAQ
      • FAQ on Kalbadevi & Girgaon
      • FAQ on Aarey
    • Facts Of Aarey
      • Note On Aarey
      • MMRC Ad
    • Quick Facts
  • Tenders
    • Civil
    • System
      • Electrical
      • Signalling & Telecom
      • Rolling Stock
      • IT
      • Depot (M&P)
      • O & M
    • Planning
    • Miscellaneous
    • Awarded Contracts
    • MMRC Contractors
    • eTender
    • EOI-MoHUA
  • Media
    • Gallery
      • Photo Gallery
      • Video Gallery
    • News
    • Newsletters
    • MD Speaks
    • Press Releases
    • Social Media
      • Facebook
      • Instagram
      • Twitter
      • Youtube
  • Careers
    • Recruitment
    • Internship Policy
  • RTI
    • RTI (GOI)
    • RTI (GOM)
    • RTI ACT 2005
    • RTI/SANAD
    • PIO/APIO
  • Vigilance
    • Chief Vigilance Officer
    • Notice
    • Vigilance Awareness
  • Contact Us
    • How to reach us
    • Compliance Officer & Company Secretary
  • Policies
Flash News
MMRC

Flash News

एनसीपीएने नूतनीकरण केलेल्या दिलीप पिरामल आर्ट गॅलरीचे मेट्रो-३ वरील छायाचित्र प्रदर्शनासह शुभारंभ
NCPA inaugurates its Renovated Art Gallery with photo exhibition on Metro Line-3
Design, Manufacture, Supply, Installation, Testing & Commissioning of Lot I: Blow Down Plant along with Comprehensive Maintenance Service, and Lot II: Well Wagon, for Project “Mumbai Metro Line-3
Design, Manufacture, Supply, Installation, Testing & Commissioning of Lot I: Blow Down Plant along with Comprehensive Maintenance Service, and Lot II: Well Wagon, for Project “Mumbai Metro Line-3
“Design, Manufacture, Supply, Installation, Testing & Commissioning and Comprehensive Maintenance Service of Rail-cum-Road Diesel Shunter” for Project Mumbai Metro Line-3
मुं.मे.रे.कॉ. तर्फे "मराठी भाषा संवर्धन पंधरवडा" साजरा मराठी बोला, मराठीतच शिका, मराठी भाषा टिकवा - अभिनेते सुमित राघवन
Civil Maintenance Contract for R & R Sites, MMRCL Transit Office and Civil & Electrical Work at MMRCL Hallmark Business Plaza 2nd & 8th Floor Offices and other allied works under Mumbai Metro Line III of MMRCL.
मुं.मे.रे.कॉ.च्या वतीने ३००० झाडांचे मूळ जागी वृक्षारोपण मोहिमेला सुरूवात
MMRC begins In-situ plantation drive of 3,000 trees
Design, Manufacture, Supply, Installation, Testing & Commissioning and Comprehensive Maintenance Service of Rail-cum-Road Diesel Shunter” for Project Mumbai Metro Line-3
  1. Home
  2. Package - 3

Package - 3

MMRC
Submitted by admin on Fri, 11/25/2016 - 09:43

Sr. No

Nature of Work

Status

1

Barricading

100 % completed. In progress with the construction works.

2

Rehabilitation & Resettlement

Completed.

3

Traffic Diversion

Completed.

4

Geo-technical investigation

100% completed.

5

Building condition Survey

Completed.

6

Tunneling Progress

Science Museum- Worli (Tansa-1) – 1382/ 1382 rings has been erected. (100 % completed)

Science Museum- Worli (Tansa-2) – 1372 / 1372 rings has been erected. (100 % completed)

 

Science Museum-Mumbai Central (Tansa-2) – 1182 / 1308 rings has been erected. (90.36 % Completed)

Science Museum-Mumbai Central (Tansa-1) – 792 / 1303 rings has been erected. (60.78 % Completed)

7

Segment Production Progress

100 % of the total scope of permanent rings has been completed.

8

Secant Piling Progress

Station Box Area:

 

Mumbai Central – 100 % completed

Mahalaxmi – 100 % completed

Science Museum – 100 % completed

Acharya Atre Chowk –100 % completed

Worli – 100 % completed

9

Traffic Decking & King Posts

 

Mumbai Central –100 % has been completed.

Mahalaxmi – 100 % has been completed.

Acharya Atre Chowk- 100 % has been completed.

Worli – 100 % has been completed.

 

 

 

10

Excavation (Station Box)

Mumbai Central:

2,14,164 / 2,14,164  cu.m ( 100% ) has been completed.

 

Mahalaxmi:

1,66,229 / 1,66,229 cu.m ( 100%) has been completed.

 

Science Museum :

2,11,816 / 2,11,816 cu.m ( 100 %) has been completed.

 

Acharya Atre Chowk:

1,87,375 / 1,87,375  cu.m ( 100 % ) has been completed.

 

Worli:

1,77,370 / 1,77,370 cu.m ( 100% ) has been completed.

 

 

11

Base Slab Progress

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100% of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

100 % of the total scope has been completed.

 

Worli:

100 % of the total scope has been completed.

 

12

Concourse Slab Progress

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100 % of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

87 % of the total scope has been completed.

 

Worli:

98 % of the total scope has been completed.

 

 

13

Roof Slab Progress

 

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100 % of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

58 % of the total scope has been completed.

 

Worli:

97 % of the total scope has been completed.

 

  14

Platform Slab Progress

Mumbai Central:

68 % of the total scope has been completed.

 

Mahalaxmi:

20 % of the total scope has been completed.

 

Science museum:

69 % of the total scope has been completed.

 

Acharya Atre Chowk:

39 % of the total scope has been completed.

 

Worli:

57 % of the total scope has been completed.

 

 

Upload File: 
PDF icon project-status-3.pdf
Date: 
Tuesday, May 31, 2022 - 09:45
Package Type: 
Package-3
Gallery: 
Package - 3 ( Mumbai Central-Mahalaxmi-Science Museum-Acharya Attre Chowk-Worli )
MMRC

Recent News

mmrc
नव्या वर्षात धावण्यासाठी भुयारी मेट्रोचे काम ऑन स्पीड
+29 Mar 2023
आरे कारशेड में उतरेगी मेट्रो-3 की नई रेक
+29 Mar 2023
CITY TO GET BACK SPACE TAKEN BY METRO 3 WORKS
+29 Mar 2023
MUMBAI STARTS RECLAIMING ROADS
+29 Mar 2023
MUMBAI STARTS RECLAIMING ROADS
+29 Mar 2023
मेट्रो ३ : रुळांचे ५८ टक्के काम पूर्ण
+27 Mar 2023
Previous Pause Next
MMRC

About MMRC

  • Tenders
  • Project
  • News
  • Contact Us
  • eTender
MMRC

Helpful Information

  • Project Route
MMRC

Policy

  • MMRC Green Policy
  • Disclaimer
  • Privacy Policy
MMRC

Other Govt Sites

  • Govt of India
  • MoHUA
  • Indian Railways
  • Govt of Maharashtra
  • MMRDA
  • Other Metros
MMRC
  • mmrc
  • mmrc
  • mmrc
MMRC

MMRC © 2019. All rights are reserved.

  • mmrc
  • mmrc
  • mmrc
Top