Skip to main content
  • Accessibility And Screen Reader Options
  • English
  • मराठी
  • हिन्दी

A A A

Homepage Logo Mumbai Metro Rail Corporation Ltd. (JV of Govt. of India and Govt. of Maharashtra)

mmrc

Search form
Home MMRC
  • Home
  • About MMRC
    • Know Your Metro
    • Our Vision, Mission & Values
    • Board of Directors
    • Key Management Team
    • Our Organization
    • Managing Director
    • Reports & Documents
    • MOA & AOA
    • Annual Report
  • Project
    • Project Route
    • Project Timeline
    • Project Funding
    • Illustrative Designs
    • Technology
    • Typical Utility Shifting Plan
    • Project Consultants
    • Benefits of Metro Line 3
    • Environmental Benefits
    • Rehabilitation & Resettlement (R&R)
      • FLGRC/SLGRC
      • Public Consultation
      • Final BSES
      • Lottery Result
      • Policy / Project Documents
      • In - situ R&R Office Address
      • BSES Survey Maps
      • Building wise Allotment List
      • Rehabilitation Building Occupation Certificate
      • Public Notices
    • Projects Reports & Documents
    • NOC
    • Notice
    • Typical Traffic Diversion Plan
  • People Connect
    • FAQ
      • FAQ on Kalbadevi & Girgaon
      • FAQ on Aarey
    • Facts Of Aarey
      • Note On Aarey
      • MMRC Ad
    • Quick Facts
  • Tenders
    • Civil
    • System
      • Electrical
      • Signalling & Telecom
      • Rolling Stock
      • IT
      • Depot (M&P)
      • O & M
    • Planning
    • Miscellaneous
    • Awarded Contracts
    • MMRC Contractors
    • eTender
    • EOI-MoHUA
  • Media
    • Gallery
      • Photo Gallery
      • Video Gallery
    • News
    • Newsletters
    • MD Speaks
    • Press Releases
    • Social Media
      • Facebook
      • Instagram
      • Twitter
      • Youtube
  • Careers
    • Recruitment
    • Internship Policy
  • RTI
    • RTI (GOI)
    • RTI (GOM)
    • RTI ACT 2005
    • RTI/SANAD
    • PIO/APIO
  • Vigilance
    • Chief Vigilance Officer
    • Notice
    • Vigilance Awareness
  • Contact Us
    • How to reach us
    • Compliance Officer & Company Secretary
  • Policies
Flash News
MMRC

Flash News

एनसीपीएने नूतनीकरण केलेल्या दिलीप पिरामल आर्ट गॅलरीचे मेट्रो-३ वरील छायाचित्र प्रदर्शनासह शुभारंभ
NCPA inaugurates its Renovated Art Gallery with photo exhibition on Metro Line-3
Design, Manufacture, Supply, Installation, Testing & Commissioning of Lot I: Blow Down Plant along with Comprehensive Maintenance Service, and Lot II: Well Wagon, for Project “Mumbai Metro Line-3
Design, Manufacture, Supply, Installation, Testing & Commissioning of Lot I: Blow Down Plant along with Comprehensive Maintenance Service, and Lot II: Well Wagon, for Project “Mumbai Metro Line-3
“Design, Manufacture, Supply, Installation, Testing & Commissioning and Comprehensive Maintenance Service of Rail-cum-Road Diesel Shunter” for Project Mumbai Metro Line-3
मुं.मे.रे.कॉ. तर्फे "मराठी भाषा संवर्धन पंधरवडा" साजरा मराठी बोला, मराठीतच शिका, मराठी भाषा टिकवा - अभिनेते सुमित राघवन
Civil Maintenance Contract for R & R Sites, MMRCL Transit Office and Civil & Electrical Work at MMRCL Hallmark Business Plaza 2nd & 8th Floor Offices and other allied works under Mumbai Metro Line III of MMRCL.
मुं.मे.रे.कॉ.च्या वतीने ३००० झाडांचे मूळ जागी वृक्षारोपण मोहिमेला सुरूवात
MMRC begins In-situ plantation drive of 3,000 trees
Design, Manufacture, Supply, Installation, Testing & Commissioning and Comprehensive Maintenance Service of Rail-cum-Road Diesel Shunter” for Project Mumbai Metro Line-3
  1. Home
  2. Package - 6

Package - 6

MMRC
Submitted by admin on Tue, 11/22/2016 - 15:03
Sr. No.Nature of WorkStatus
1Tunneling & Segment Production Progress CSIA T2 Metro Station
Tunnel CSIA T2 to Sahar Road Station (Downline):
Permanat Ring: Total Progress - 491, Scope - 491
Completed
Permanat Ring: Total Progress - 491, Scope - 491
Completed
Tunnel MVS to CSIA T1 (Upline):
Permanat Ring: Total Progress - 910, Scope - 910
Completed
Tunnel MVS to CSIA T1 (Downline):
Permanat Ring: Total Progress - 892, Scope - 892
Completed
Sahar Road Station to CSMIA
Domestic Airport Station (Downline)
Permanat Ring: Total Progress - 1080, Scope - 1080
Segment Production Progress:
Permanent Rings: Total progress - 4949, Scope - 4949
2Excavation CSIA T1 Metro station
 Total progress - 268971 Cum. Scope - 268471 Cum. (Work in progress)
Sahar road Station
Total progress - 322478 Cum. Scope - 322478 Cum. (Completed)
CSIA T2 Metro Station
Total progress - 468642 Cum. Scope - 468642 Cum. (Completed)
3Base Slab Progress CSIA T1 Metro station:
Base Slab Completed.
Concourse Slab:  Total progress - 196 m. Scope - 198 m. (Work in progress)
Concourse to Roof Slab:  Total progress - 370 m. Scope - 390 m. (Work in progress)
Roof Slab:  Total progress - 196 m. Scope - 198 m. (Work in progress)
CSIA T2 Metro Station: 
Base Slab Completed.
Concourse Slab:  Total progress - 311 m. Scope - 314 m. (Work in progress)
Concourse to Roof Wall:  Total progress - 499 m. Scope - 541 m. (Work in progress)
Roof Slab:  Total progress - 311 Cum. Scope - 314 m. (Work in progress)
Sahar Road Metro station: 
Base Slab Completed.
Concourse Slab:  Total progress - 220 m. Scope - 220 m. (Completed)
Concourse to Roof Slab:  Total progress - 328 m. Scope - 328  m. (Completed)
Roof Slab:  Total progress - 220 Cum. Scope - 220 m. (Completed)
4Secant Piling Progress CSIA T1 Metro station
Secant piles: Total progress - 808, Scope - 808
Micro piles: Total progress - 154, Scope - 154
Sahar road Station
Secant piles: Total progress - 1121, Scope - 1121
Subway secant piles: Total progress - 67, Scope - 67
CSIA T2 Metro Station
Secant piles: Total progress - 1298, Scope - 1298
5Rehabilitation & Resettlement ______
6Building condition SurveyPre-condition survey this week - 0
Total Progress - 60
Scope - 60
7Tree Cutting/transplantationCSIA T1 -  Total progress - 3 , Scope - 3 ,  Completed
Transplantation - 60 out of 112
Sahar Rorad - Total progress - 4 , Scope - 4 , Completed
Transplantation - 177 out of 226
CSIA T2 - Total progress - 0 , Scope - 0 , Completed
Transplantation -  4 out of 4 completed
8Traffic DiversionSAHAR ROAD STATION:
Road diversion: Stage-1 Completed
Subway completed
Sahar Shadow Road:
Commissioned on 27th July 2018.
Caping beam & Flood Wall: Completed
CSIA T2 Metro Station:
Internal Road: Completed.
Ancillary Works for TBM Launching: Completed
9Geo-technical investigationSAHAR Road Metro station
Completed
Sahar Road to International Station
CSIA T1 Metro Station
Completed
CSIA T2 Metro Station
Completed
10BarricadingSAHAR Road Metro station
All construction Works is going on within
secured barricading area .
CSIA T1 Metro station
Completed
CSIA T2 Metro station
Completed
Construction Depot JVLR (GI Sheets)
Completed
Upload File: 
PDF icon project-status-6.pdf
Date: 
Tuesday, June 21, 2022 - 15:00
Package Type: 
Package-6
Gallery: 
Package - 6 (CSA(domestic)-CSA(international)-Sahar )
MMRC

Recent News

mmrc
नव्या वर्षात धावण्यासाठी भुयारी मेट्रोचे काम ऑन स्पीड
+29 Mar 2023
आरे कारशेड में उतरेगी मेट्रो-3 की नई रेक
+29 Mar 2023
CITY TO GET BACK SPACE TAKEN BY METRO 3 WORKS
+29 Mar 2023
MUMBAI STARTS RECLAIMING ROADS
+29 Mar 2023
MUMBAI STARTS RECLAIMING ROADS
+29 Mar 2023
मेट्रो ३ : रुळांचे ५८ टक्के काम पूर्ण
+27 Mar 2023
Previous Pause Next
MMRC

About MMRC

  • Tenders
  • Project
  • News
  • Contact Us
  • eTender
MMRC

Helpful Information

  • Project Route
MMRC

Policy

  • MMRC Green Policy
  • Disclaimer
  • Privacy Policy
MMRC

Other Govt Sites

  • Govt of India
  • MoHUA
  • Indian Railways
  • Govt of Maharashtra
  • MMRDA
  • Other Metros
MMRC
  • mmrc
  • mmrc
  • mmrc
MMRC

MMRC © 2019. All rights are reserved.

  • mmrc
  • mmrc
  • mmrc
Top