Skip to main content
  • Accessibility And Screen Reader Options
  • English
  • मराठी
  • हिन्दी

A A A

Homepage Logo Mumbai Metro Rail Corporation Ltd. (JV of Govt. of India and Govt. of Maharashtra)

mmrc

Search form
Home MMRC
  • Home
  • About MMRC
    • Know Your Metro
    • Our Vision, Mission & Values
    • Board of Directors
    • Key Management Team
    • Our Organization
    • Managing Director
    • Reports & Documents
    • MOA & AOA
    • Annual Report
  • Project
    • Project Route
    • Project Timeline
    • Project Funding
    • Illustrative Designs
    • Technology
    • Typical Utility Shifting Plan
    • Project Consultants
    • Benefits of Metro Line 3
    • Environmental Benefits
    • Rehabilitation & Resettlement (R&R)
      • FLGRC/SLGRC
      • Public Consultation
      • Final BSES
      • Lottery Result
      • Policy / Project Documents
      • In - situ R&R Office Address
      • BSES Survey Maps
      • Building wise Allotment List
      • Rehabilitation Building Occupation Certificate
      • Public Notices
    • Projects Reports & Documents
    • NOC
    • Notice
    • Typical Traffic Diversion Plan
  • People Connect
    • FAQ
      • FAQ on Kalbadevi & Girgaon
      • FAQ on Aarey
    • Facts Of Aarey
      • Note On Aarey
      • MMRC Ad
    • Quick Facts
  • Tenders
    • Civil
    • System
      • Electrical
      • Signalling & Telecom
      • Rolling Stock
      • IT
      • Depot (M&P)
      • O & M
    • Planning
    • Miscellaneous
    • Awarded Contracts
    • MMRC Contractors
    • eTender
    • EOI-MoHUA
  • Media
    • Gallery
      • Photo Gallery
      • Video Gallery
    • News
    • Newsletters
    • MD Speaks
    • Press Releases
    • Social Media
      • Facebook
      • Instagram
      • Twitter
      • Youtube
  • Careers
    • Recruitment
    • Internship Policy
  • RTI
    • RTI (GOI)
    • RTI (GOM)
    • RTI ACT 2005
    • RTI/SANAD
    • PIO/APIO
  • Vigilance
    • Chief Vigilance Officer
    • Notice
    • Vigilance Awareness
  • Contact Us
    • How to reach us
    • Compliance Officer & Company Secretary
  • Policies
    • RISK ASSESSMENT & MANAGEMENT POLICY
    • WHISTLE BLOWER POLICY
    • CORPORATE SOCIAL RESPONSIBILITY POLICY
Flash News
MMRC

Flash News

Licensing of Spare Optic Fibre Cables & Right of Way For Laying Additional Cables At Mumbai Metro Line 3
Licensing of Spare Optic Fibre Cables & Right of Way For Laying Additional Cables At Mumbai Metro Line 3
Licensing of Spare Optic Fibre Cables & Right of Way For Laying Additional Cables At Mumbai Metro Line 3
Licensing of Spare Optic Fibre Cables & Right of Way For Laying Additional Cables At Mumbai Metro Line 3
Public Notice
‘Appointment of Transaction Advisor for disposal of plot at Nariman Point for Metro Line 3’
‘Appointment of Transaction Advisor for disposal of plot at Nariman Point for Metro Line 3’
'Station Semi-Naming & Branding Rights at Mumbai Metro Line 3 (Stage-2)' RFP
Supplying consumable materials and maintenance of Electrical installations at Transit Office building of MMRCL at BKC, Bandra (E) in Mumbai for 2 years (2023- 2025)
Supplying consumable materials and maintenance of Electrical installations at Transit Office building of MMRCL at BKC, Bandra (E) in Mumbai for 2 years (2023- 2025)
  1. Home
  2. Package
  3. Weekly progress report for package-3
mmrc icon

Weekly progress report for package-3

MMRC

Updated as on: 31st May 2022

Sr. No

Nature of Work

Status

1

Barricading

100 % completed. In progress with the construction works.

2

Rehabilitation & Resettlement

Completed.

3

Traffic Diversion

Completed.

4

Geo-technical investigation

100% completed.

5

Building condition Survey

Completed.

6

Tunneling Progress

Science Museum- Worli (Tansa-1) – 1382/ 1382 rings has been erected. (100 % completed)

Science Museum- Worli (Tansa-2) – 1372 / 1372 rings has been erected. (100 % completed)

 

Science Museum-Mumbai Central (Tansa-2) – 1182 / 1308 rings has been erected. (90.36 % Completed)

Science Museum-Mumbai Central (Tansa-1) – 792 / 1303 rings has been erected. (60.78 % Completed)

7

Segment Production Progress

100 % of the total scope of permanent rings has been completed.

8

Secant Piling Progress

Station Box Area:

 

Mumbai Central – 100 % completed

Mahalaxmi – 100 % completed

Science Museum – 100 % completed

Acharya Atre Chowk –100 % completed

Worli – 100 % completed

9

Traffic Decking & King Posts

 

Mumbai Central –100 % has been completed.

Mahalaxmi – 100 % has been completed.

Acharya Atre Chowk- 100 % has been completed.

Worli – 100 % has been completed.

 

 

 

10

Excavation (Station Box)

Mumbai Central:

2,14,164 / 2,14,164  cu.m ( 100% ) has been completed.

 

Mahalaxmi:

1,66,229 / 1,66,229 cu.m ( 100%) has been completed.

 

Science Museum :

2,11,816 / 2,11,816 cu.m ( 100 %) has been completed.

 

Acharya Atre Chowk:

1,87,375 / 1,87,375  cu.m ( 100 % ) has been completed.

 

Worli:

1,77,370 / 1,77,370 cu.m ( 100% ) has been completed.

 

 

11

Base Slab Progress

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100% of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

100 % of the total scope has been completed.

 

Worli:

100 % of the total scope has been completed.

 

12

Concourse Slab Progress

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100 % of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

87 % of the total scope has been completed.

 

Worli:

98 % of the total scope has been completed.

 

 

13

Roof Slab Progress

 

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100 % of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

58 % of the total scope has been completed.

 

Worli:

97 % of the total scope has been completed.

 

  14

Platform Slab Progress

Mumbai Central:

68 % of the total scope has been completed.

 

Mahalaxmi:

20 % of the total scope has been completed.

 

Science museum:

69 % of the total scope has been completed.

 

Acharya Atre Chowk:

39 % of the total scope has been completed.

 

Worli:

57 % of the total scope has been completed.

 

 

MMRC

Recent News

mmrc
2024 में दौड़ेगी मेट्रो-3
+30 Nov 2023
MMRC को 'टनलिंग प्रोजेक्ट ऑफ द ईयर' अवार्ड
+24 Nov 2023
उन्नत मार्ग... भूमिगत मार्गासाठी भगीरथ प्रयत्न
+24 Nov 2023
मेट्रो सामान्यांना परवडली पाहिजे !
+24 Nov 2023
मेट्रो-३ प्रकल्पाचा विशेष गौरव
+24 Nov 2023
मुंबई मेट्रो रेल कॉर्पोरेशन 'टनेलिंग प्रोजेक्ट ऑफ दि इअर' पुरस्काराने सन्मानित
+24 Nov 2023
MMRC

About MMRC

  • Tenders
  • Project
  • News
  • Contact Us
  • eTender
MMRC

Helpful Information

  • Project Route
MMRC

Policy

  • MMRC Green Policy
  • Disclaimer
  • Privacy Policy
MMRC

Other Govt Sites

  • Govt of India
  • MoHUA
  • Indian Railways
  • Govt of Maharashtra
  • MMRDA
  • Other Metros
MMRC
  • mmrc
  • mmrc
  • mmrc
  • mmrc
MMRC

MMRC © 2019. All rights are reserved.

Maintained by Best IT Company in Ludhiana

  • mmrc
  • mmrc
  • mmrc
  • mmrc
Top